Prepare the information
An existing schedule, a project discussion, or a file listing proposed items can be your starting point. Select the important information before entering it into OPUS. For each proposed item, establish:- A name that identifies its scope.
- Whether it is an activity or a milestone.
- A starting and delivery date for an activity, or one date for a milestone.
- An optional group.
- A predecessor, if a dependency is meaningful.
- Whether the dates are agreed, estimated, or still uncertain.
Open Planning
Open the project’s Planning page and select Table. If there are no items yet, you can start with Add your first activity or New activity. A blank planning is not a ready-made project schedule; its meaningful information still needs to be supplied.Create groups when they help
- Select Create a group.
- Enter a meaningful group name.
- Submit the group.
Create an activity
- In the intended group, select New activity.
- Edit Activity Name to describe the period of work.
- Set Starting Date and Delivery Date.
- Review the resulting dates before creating the next item.
Create a milestone
- In the intended group, select New milestone.
- Give it a name describing the event.
- Set Delivery Date to the event’s date.
Connect dependent items
In an item’s Dependency field, choose the item it depends on. For example, on Install external windows, select Windows delivered. Set the dependency on the successor. Adding the link does not adjust its dates automatically. Use only meaningful dependencies. You can leave the field empty.Review the Gantt
Select Gantt and check the whole schedule:- Do the important activities cover the intended project periods?
- Are major milestones visible at the correct dates?
- Are overlaps intentional?
- Are dependency directions correct?
- Have any creation defaults been left in place?
- Can someone unfamiliar with the detailed operational schedule understand the overview?
Example: a selected window package overview
The following dates are illustrative, not a template or a recommendation for construction durations.
This overview communicates the important sequence. It does not reproduce every manufacturing task, delivery movement, or installation operation.